Nepal Govt. Regd. No. 1224/064, SWC Affiliation No. 22612

Devi Jal Kumari Lower Secondary School

Devi Jal Kumari Lower Secondary School was established in 2001 AD (2058 BS). It is located in Ward No 6 Aprik village of Arughat Rural Municipality (previously Ward No 6 of Aruarbang Village Development Committee) in northern Gorkha district. The school has 215 students running classes from grade 1 to 8. It employs 10 staff members. The original two level school building was constructed by villagers 55 years ago and was already partly condemned before the earthquake.

Even before the earthquake, the school was in a dilapidated condition. And we had made a plan to renovate it. Then the earthquake happened. The entire school buildings and all the houses of the villages collapsed. 4 people died and 20 sustained serious injuries. The principal of the school was trapped under the rubbles and taken out alive. You can see the destruction of the village in this video: Video Link

This school provides education to 215 students from grade 1 to 8 and currently has 10 staff members. During the earthquake, it lost all 5 buildings, 1 staff room and the library along with almost all furniture and fixtures in these buildings. Its toilet facility however, suffered minimum damage, which can be reused after some minor repairs. Currently the school is open. The students are taught in temporary rooms built from aluminum sheets supported by bamboo. We distributed 240 corrugated aluminum sheets to the school in one of our earthquake aid distribution trips to Gorkha. But it is quite difficult for the school to teach the students in the absence of proper school facilities.

We are planning to build 2 earthquake-proof school buildings with 12 rooms. This includes 8 classrooms, an office/staff room, a library/reading room, a Montessori-style nursery room and a store room. In addition to that, 3 toilets for staff and for girls and boys will also be built within school compound.

Due to lack of enough funds, we divided the work load into different phases. In phase I our aim was to construct a four-room school block which we achieved in early April 2017. In phase II, our aim was to add four roomed second storey on the same block which is currently on progress and will be over by March 2018.

We were planning for phase III. But, now the remaining part of the school will be constructed by Japan International Cooperation Agency (JICA). After JICA completes the construction, we are planning to add educational facilities to the school such as a computer lab and a library.

After the earthquake, Sambhav Nepal visited many villages in Northern Gorkha to assess the extent of the damage and offer assistance to the communities with the immediate focus being on distributing food to the villages and providing temporary shelter to the schools. It was during these visits we identified that our long-term resources and assistance would be best utilized by rebuilding the schools and so we set about planning our school-rebuilding mission.

PROJECT UPDATE – JUNE 2022

With the generous donation of Rotary Club of Kalamalka, Vernon BC ,Canada and Nepal One Day at A Time, Mary Jackson, the past president of club, and Patti Lefkos together with her husband Barry Hodgins, a two-storey eight roomed school building was constructed for Shree Devi Jal Kumari Secondary School on 2019.

As COVID-19 pandemic hit the whole world, Nepal government also imposed nationwide lockdown for a very long period of time. This resulted in deterioration of the school as well. The Sambhav Nepal made building needed maintenance and repair so that the students can study in safe and sound environment.

Apart from this, the school also needed a well-equipped computer lab and electrical repair maintenance.

With the generous donation from Rotary Club of Kalamalka, Vernon BC, on 8th June 2022, we handed over below mentioned goods to Shree Devi Jal Kumari Secondary School in the presence of Mr. Prem K. Khatry (Founder, Sambhav Nepal), Ms. Kalpana Nepali (Vice-president, Arughat Rural Municipality), Mr. Rajeeb Gurung (President, Ward No.7, Arughat Rural Municipality) & Mr. Jeevan Gurung (Principle, Shree Devi Jal Kumari Secondary School).

The goods which were handed over to Shree Devi Jal Secondary School are below:

SN Particulars No.
1 Desktop Computer 17 pcs
2 Desktop Computer Table & Chair Set 17 pcs
3 Kindergarten Goods As per the need
4 UPS for Desktop Computer 17 pcs
5 Book Rack 7 pcs
6 Printer with Scanner 1 pcs
7 WiFi Router 2
8 Electrical Wiring, Interior Fixing and Painting As per the need

All of these goods, repair and maintenance were done under ‘Computer & Furniture Aid for School Project 2078’. This project was highly appreciated by the locals, the local government, students and teachers of Shree Devi Jal School.

Please check the below link for the backstory Shree Devi Jal Kumari School, and handover program of  ‘Computer & Furniture Aid for School Project 2078’

https://www.youtube.com/watch?v=a1s_8DZNiD8

The handover program’s news was published in online/print medium of Daraudi News. Please check media coverage section to read the news online.

February Progress Update – 2019

The two-storey block which we made in Phase I and II has been handed over to the school administration. After this, we constructed the toilets for Devi Jal Kumari. The students are currently using them and are happy with clean and modern toilets.

Japan International Cooperation Agency (JICA) will be taking over from us to construct the remaining part of the school. And, after JICA completes the work, our future plan is to make a computer lab and a library for the school.

Devi Jal Kumari Toilet

August Progress Update – 2018

The construction work of Devi Jal Kumari Lower Secondary School has finally come into completion. The building is ready to accommodate students and the classes are ready to be used. Painting, and furnishing of the rooms has successfully ended. The ground needs to be cleared which will be done after the monsoon gets over. With this the phase II of Devi Jal Kumari has finally ended and the upper floor is ready for the children.

Devi-Jal-August-Front The final look of the School

Devi-Jal-August-Side The side look of the building

June Progress Update – 2018

The construction work of Devi Jal Kumari Lower Secondary School is in progress and is undergoing the plasterworks of the first floor at the moment. The roofing of the building is completed, now leaving painting and furnishing of the classrooms. The monsoon rain has started thus delaying the work slightly. The students of the school are in summer and monsoon vacation as well. Therefore, in the absence of the students the construction work will be in progress aiming for the completion as soon as possible.

May Progress Update – 2018

The ongoing construction of four rooms in Devi Jal Kumari is on the verge of completion. The construction was supposed to be completed within this month but due to few problems that kept arising, the work couldn’t be completed. With the ongoing summer, the village suffered a water shortage. Water springs dried up hence the amount of water required for curing and mixing was not enough thus delaying the final work. Monsoon has now started hence giving rise to the spring water. The construction work has resumed and is expected to complete by the end of July. With the completion of the final work, the school will be handed over to the school authorities.

March Progress Update – 2018

The construction of the four rooms in the upper floor of Devi Jal Kumari is taking place since November 2017. The construction of the school is slightly delayed due to lack of construction materials. The shortage of bricks from the supplier resulted into the postponing of the completion of work. The construction was scheduled to be completed by March 2018 but now due to the inconvenience the work will be completed only by the end of May 2018. With the beginning of the new school year session in May, the school will be completely ready and handed over to the school authorities.

Upon completion of the construction of this building, Sambhav Nepal has proposed to construct a 4-room toilet block for the school. The proposal has been submitted at Social Welfare Council (the government authority that looks after the all NGOs projects) and once it is approved, the construction will start and be completed within 2 months.

Phase II

As soon as the first phase completed, we set our goals for phase II in which we aimed to add four rooms in the upper floor of the block we built in the first phase. The work for the second started from November and is ongoing. We are going to complete the work for this stage by March 2018. The project has approval from concerned government authorities such as District Office of Gorkha and Social Welfare Council of Nepal.

Completion of Phase I – April 2017

For successfully completing the Phase I, on April 25, 2017, we held an inauguration ceremony. In this phase, we completed the construction of a four-room school block. The ceremony involved our key donors: Mary Jackson, the Past President of Kalamalka Rotary Club of Vernon, B.C., Canada, and Patti Lefkos and Barry Hodgins, the generous people behind Nepal One Day at a Time.

We have received commitments from our donors for the Phase II of the project. We will begin it when the monsoons end in Nepal. In Phase II, we will add four-room second storey on the same block.

Progress Update – February 2017

Back in December 2016, we finished building the foundation for the hostel building. And by the month of February, we have erected walls and pillars.

Progress Update – January 2017

In December 2016 we had estimated we would complete the foundation by January 2017. So, by that time we completed the foundation and moved to erecting the pillars and making the walls and all. With this, we completed 30% of the total work of the first phase.

Construction Started – November 2016

We had planned to start the actual construction after the monsoon as the rains made the dirt roads very difficult to pass and caused landslides.The conditions were not favorable to transport the construction materials.

The monsoon overstayed this year. As planned we started construction only from November. Foundation is considered 30% of the whole construction. And by December we were building the foundation.

Site Preparation – September 2016

In September 2016, we prepared the site where the new buildings will be constructed. With the help of a bulldozer and local volunteer laborers, we brought the ground at equal level and hardened the land.

Foundation Stone Laying (Cornerstone) Ceremony – April 2016

On 25th April 2016, stone laying (cornerstone) ceremony of Devi Jal Kumari Lower Secondary School – Arupokhari, was successfully inaugurated by Prem K Khatry Founder of Sambhav Nepal. This means, we have started a construction of school, where we will rebuild four class rooms in a block. Meeting was held among the Building Construction Committee and Sambhav Nepal volunteer, where strict instruction was given not to compromise with quality of raw materials used for the sustainable development of our project.

Computer & Furniture Aid For School Project In Shree Devi Jal Kumari Secondary School

Toilets for Devi Jal Kumari School

Two-Storey Block After Completion

Pictures of Devi jal After Completion of Phase I

Progress Update - January 2017

Construction Started - November 2016

Site Preparation - September 2016

Foundation Stone Laying Ceremony - April 2016

Earthquake Damages and Aid to School

Devi Jal Kumari Lower Secondary School Prior Earthquake

Devi Jal Kumari School Computer Lab